Flagship Urban Project · Active Construction

Chiro City
Corridor Project

A 3.2 km landmark urban transformation — smart infrastructure, green corridors, mixed-use development, and IoT integration reshaping Chiro's heartland.

3.2km
Corridor Length
$240M
Total Investment
14
Sub-Projects
8,400
Jobs Created
2027
Completion Target
LIVE
IoT Monitoring

Transforming Chiro's Urban Heartland

The Chiro City Corridor Project is the most ambitious urban regeneration initiative in the city's history. Spanning 3.2 kilometres from the Central Market District to the New Administrative Quarter, it integrates world-class architecture with cutting-edge smart city technology.

Every element — from the fibre-optic smart lighting to the underground utility spine and AI-monitored green spaces — is designed to function as a living, breathing digital infrastructure layer for the next 50 years.

Smart IoT Spine

480 embedded sensors across the full corridor length.

Green Corridors

2,400 trees and 18,000 m² of landscaped parkland.

Smart Mobility Lane

Dedicated EV, bike, and micro-mobility lanes with charging hubs.

Mixed-Use Development

12 buildings: residential, commercial, civic, and cultural.

Construction Roadmap

Four integrated phases delivering the corridor's full vision from 2022 through 2027.

Phase 1 ✓ Complete
2022–23

Foundation & Utility Spine

Underground infrastructure: fibre-optic backbone, smart water/power grid, flood drainage system, and 3.2km utility tunnel installation.

Progress100%
Phase 2 ✓ Complete
2023–24

Road & Mobility Infrastructure

Smart roadway with embedded traffic sensors, dedicated EV lanes, automated bike lanes, 3 smart intersections with AI signal control.

Progress100%
Phase 3 In Progress
2024–26

Buildings & Public Spaces

12 mixed-use buildings, 3 public plazas, 5 smart parks, city library, innovation hub, civic centre — with IoT integration throughout.

Progress72%
Phase 4 Upcoming
2026–27

AI Integration & Activation

Full AI traffic management, predictive maintenance systems, AR information kiosks, smart event plazas, and official corridor inauguration.

Progress18%

Key Milestones

March 2022
Project Groundbreaking
Official launch ceremony attended by City Council and regional authorities. Phase 1 excavation begins.
December 2022
Underground Spine Complete
3.2km utility tunnel, fibre backbone, and smart water system installed on schedule.
August 2023
Smart Roadway Opened
Phase 2 complete — EV lanes, AI intersections, and smart parking all active for public use.
July 2025 — NOW
Buildings 70% Complete
8 of 12 mixed-use buildings topped out. 3 smart parks open to public. Innovation hub opens Q4 2025.
Q2 2026
Civic Centre Opens
New city library, cultural centre, and government service hub to open with full IoT integration.
December 2027
Full Corridor Inauguration
Complete 3.2km corridor activated — all 14 sub-projects operational and AI management system live.

Sub-Project Tracker

Smart Road & EV InfrastructureDone
Residential Tower A & B88%
Commercial Plaza & Market75%
Smart Parks & Green Corridors60%
Civic Centre & Library40%
AI Management System18%
Full Gallery
Main Corridor
Aerial View
Green Zones
Mobility Lane
Civic Buildings
IoT Sensors
Join the Transformation

Stay Updated on the Corridor Project

Subscribe for monthly progress reports, construction updates, and public consultation invitations.

View Gallery Project Data Contact Team